Here’s another snapshot of the unit 1 boiler under construction and construction progressing on unit 2. The structure for the U1 and U2 elevator is clearly visible. The units 1 & 2 turbine deck is there. One of the yellow Bechtel trucks we used to see all over town is in the foreground. Click the image to enlarge.
When did the NGS go online?
LikeLike
If I remember correctly, it was 1974, 1975, and 1976 for Units 1, 2, and 3 respectively.
LikeLike
Thank you for your response to my question of when the NGS went online!
LikeLike
When I hired on in late ‘74, unit 1 was on line, unit 2 was doing steam blows (cleaning out the steam lines leading to the turbine) and unit 3 was the “spare parts” source for units 1 & 2 😁